Housing fast-track: what section 246e means for landlords
The housing fast-track may ease planning restrictions for new homes. We explain its conditions and limits and work through a landlord's rooftop extension.
Your block of flats has three storeys, and the binding local development plan [Bebauungsplan] permits exactly three. Adding a fourth storey for two roof-level flats may require a plan amendment or another planning route. Since 30 October 2025, the housing fast-track provision [Bau-Turbo] under section 246e of the Federal Building Code [Baugesetzbuch, BauGB] has provided an additional route for approving housing.
This matters to landlords in two ways. Subject to certain conditions, they may be able to create housing more quickly themselves. And more development may become possible on the plot next door than the local development plan provides for. We explain both implications and work through a rooftop extension example.
01What section 246e BauGB allows
The provision is headed “Temporary special provision for residential construction”. It forms part of the Act to Accelerate Residential Construction and Safeguard Housing [Gesetz zur Beschleunigung des Wohnungsbaus und zur Wohnraumsicherung] and took effect on 30 October 2025.
In essence, section 246e enables departures from the Federal Building Code and regulations based on it, subject to municipal consent. These may include provisions in a local development plan governing the number of storeys or permitted uses. Three central conditions apply; they do not replace a full assessment of the proposal.
- 01Housing is created
A new residential building, an extension, alteration or renewal that creates homes, or the conversion of a building to residential use. Complementary uses such as nurseries, medical practices or a shop serving the neighbourhood may be included subject to subsection 5.
- 02Public interests and neighbours' interests are considered
The departure must be compatible with public interests, with due consideration given to neighbours' interests. Environmental assessment requirements and grounds for exclusion must be considered separately. Significant additional environmental effects cannot automatically be overcome simply by carrying out an environmental assessment.
- 03The municipality consents
Municipal consent, or consent deemed granted under the statutory provisions, is required. The municipality assesses the proposal against its planning objectives.
In outlying areas outside established development [Außenbereich], the provision has a geographical limit: the statutory spatial relationship with built-up areas or areas covered by development plans must exist (subsection 3). The precise boundary requires assessment for the plot concerned. The expiry date of 31 December 2030 concerns use of the special provision, not the validity period of a permit granted under it (subsection 4). The permit's own validity and expiry rules still apply. Where necessary, ask a lawyer specialising in German construction and planning law to assess the planning requirements for your plot.
02Municipal consent: three months
Section 36a BauGB governs municipal consent. The municipality's planning objectives are central to its assessment. Consent may be linked to commitments by the developer, for example concerning green space, dwelling sizes or subsidised housing, where legally permissible.
Municipalities may adopt their own consent guidelines. Before commissioning plans, ask the local building authority whether any such guidelines exist and which requirements apply to your plot.

03What the housing fast-track does not change
The name suggests a clear run. That is not what it provides.
State building regulations still apply. Boundary distances, fire safety, parking and accessibility are governed in particular by the relevant state law. Section 246e does not create a general exemption from these requirements. Other applicable rules must also be observed.
Costs and interest remain. The provision may ease planning procedures. It does not automatically reduce construction costs or financing rates. High costs may prevent implementation even after approval. A permit alone therefore does not make a proposal a financially viable construction project. You also need sustainable financing, a robust cost plan and the necessary construction capacity.
Neighbours can seek legal remedies. Municipal consent can generally be challenged in connection with the development approval. Whether neighbours can successfully challenge a building permit depends in particular on a possible infringement of their own legally protected rights. Not every adverse effect on their interests is sufficient. Ask a qualified lawyer to assess the remedies available in the individual case.
Approval is not automatic. The provision does not confer an unconditional entitlement to consent or a permit. Without the necessary express or deemed consent, this approval route is unavailable; other planning routes require separate assessment.
04Is the housing fast-track working yet?
An increase in building permits alone does not show how much of that growth is attributable to the housing fast-track. Aggregate figures also include projects approved under other planning provisions. Financing, construction costs, demand and projects prepared over a longer period also influence the trend. A meaningful assessment depends on which projects are actually approved under section 246e, whether their procedures become shorter and how many are subsequently built.
Approval and completion must also be distinguished. Financing, procurement and construction follow approval, and some projects can be delivered more quickly than others. A simpler approval procedure may therefore have an effect before it becomes visible in the number of homes ready for occupation. The impact on supply remains delayed and project-specific. The guide to housing construction in 2026 discusses completions and housing needs.
05Worked example: two flats on the roof
Mr Kaya owns a block containing six flats. He is single and has taxable income of €90,000 before the additional rental result. With municipal consent and the necessary building permit, he adds a storey containing two flats with a combined floor area of 120 m². The name is fictional; the following illustrative calculation is simplified and is not a forecast.
We assume costs of €4,200/m² including design and planning, giving a total of €504,000. Mr Kaya contributes 30% equity, or €151,200, and borrows €352,800 at an assumed interest rate of 3.8%, with initial annual principal repayments of 2%. He lets the new flats at a rent excluding service charges [Kaltmiete] of €13.50/m² per month. Costs, interest and rent are assumptions solely for this example.
For the simplified annual calculation, we apply the interest rate and initial repayment rate to the original loan amount. With a repayment mortgage serviced monthly, the split between interest and principal changes during the first year. The table is therefore not an exact repayment schedule. Costs not recoverable from tenants are assumed to equal 10% of rent. The illustrative tax calculation assumes these are expenses actually incurred and immediately deductible. Reserve contributions are excluded. Payments into an owners' association maintenance reserve [Erhaltungsrücklage] are not immediately deductible: the relevant amounts are actual eligible expenditure, not the full service charge paid by the owner [Hausgeld].
For depreciation, we assume that the existing building was completed between 1925 and 2022 and that the additional storey constitutes subsequent capitalised construction expenditure on that building for tax purposes, rather than a separate new building. The full €504,000 is treated as depreciable construction expenditure. This gives straight-line depreciation of 2% in the model under section 7(4) of the Income Tax Act [Einkommensteuergesetz, EStG]. We calculate the income tax saving on a simplified basis as 42% of the tax loss. Solidarity surcharge and church tax are excluded. Discuss the actual tax classification and qualifying cost basis with your tax adviser.
| Amount | |
|---|---|
| Rent: 120 m² × €13.50 × 12 | €19,440.00 |
| Interest: simplified 3.8% on €352,800 | −€13,406.40 |
| Initial principal repayment: 2% of €352,800 | −€7,056.00 |
| Costs not recoverable from tenants: assumed at 10% of rent | −€1,944.00 |
| Cash flow before tax | −€2,966.40 |
| Depreciation: 2% straight-line on €504,000 in the model | €10,080.00 |
| Calculated tax loss under these assumptions | −€5,990.40 |
| Income tax saving: simplified 42% of the loss | +€2,515.97 |
| Cash flow after income tax in the model | −€450.43 |
| Monthly cash flow after income tax in the model | −€37.54 |
The monthly cash shortfall before tax is approximately €247. After the modelled income tax saving, it is approximately €38. That tax saving is not automatically available as cash each month. The simplified calculation includes €7,056 of annual principal repayments. Assumed construction costs are 25.9 times annual rent, or roughly 26 years' rent; this is not a comprehensive measure of investment returns.
The calculation is sensitive to changes. At 4.1% rather than 3.8% interest, with initial principal repayments still at 2%, the pre-tax shortfall rises to approximately €335 a month. After the income tax saving calculated at 42%, it is approximately €89, with all other assumptions unchanged. If construction costs rise by 10% and the entire additional €50,400 is borrowed at 3.8% interest with 2% initial principal repayments, monthly debt service increases by approximately €244 before tax. This excludes any other cost changes. The housing fast-track may ease the approval process; the project must still stand up financially.

06Development next door: what buyers of an existing flat should check
The local development plan sets out planning provisions for the neighbouring plot. However, statutory exceptions, exemptions and plan amendments could already be possible before the housing fast-track. Until the end of 2030, section 246e provides an additional route for departures. With municipal consent and the other requirements met, denser or taller development may be possible next door. The guide to reading a local development plan explains how to interpret one.
- 01Are there vacant plots or low-rise neighbouring buildings?
These may offer opportunities for additional development; their presence does not establish any specific development intention.
- 02Has the municipality issued housing fast-track guidelines?
Ask the building authority about published criteria and their application to the neighbourhood.
- 03Have planning applications been submitted?
Ask the property manager and building authority about known ongoing proceedings. Whether, and to what extent, you can obtain information or inspect files requires separate clarification.
- 04What would development mean for your flat?
Reduced daylight or views may affect its appeal to tenants. Additional homes and new shops may also bring more activity to the neighbourhood.
07Who might benefit from the housing fast-track?
- You own an entire block of flats with development potential in the roof or grounds.
- You have equity and can cover a construction period without rental income from the new homes.
- Your municipality has substantial housing needs and signals support for suitable projects.
- You own a single flat and want to proceed without the necessary involvement of the other owners.
- Your project only works with very low construction costs or interest rates.
- Structural, fire safety or parking requirements cannot be met for the extension.
08Risks and limitations
Construction costs and timing. Adding storeys may reveal unexpected structural, roof or building-services issues. The 10% cost increase considered in the example is only a scenario, not a universally sufficient contingency. Obtain a project-specific assessment of the contingency required. Interest may accrue during construction before the new flats generate rent.
Interest rates. The example assumes 3.8%. Your decision should be based on actual financing offers for the project. Compare not only the interest rate but also the fixed-rate period, principal repayments, interest charged on undrawn funds and conditions for releasing the loan. Each additional 0.1 percentage point adds €352.80 to annual interest calculated on the initial loan amount of €352,800. Read more in what determines mortgage interest rates?.
Expiry. Anyone starting a project in 2030 should examine the timing requirements particularly carefully. Starting the design process or submitting an application does not automatically secure use of the special provision. A permit issued in time remains subject to its own validity rules. Ask a qualified lawyer to assess the legal deadlines for your project.
Letting. The new flats need to attract tenants at the assumed rent. Section 556f of the Civil Code [Bürgerliches Gesetzbuch, BGB] provides an exemption from the initial rent cap [Mietpreisbremse] for homes first occupied and let after 1 October 2014. Whether the newly created flats meet the conditions requires a project-specific assessment. Subsequent rent increases depend on the tenancy agreement and applicable legislation. For increases under section 558 BGB, the local reference rent and statutory increase limit are particularly relevant; stepped and index-linked rents follow different rules. Ask a qualified lawyer about any uncertainty concerning rental terms.
Tax. Depreciation for an additional storey depends, among other things, on its tax classification, the relevant completion date and the qualifying cost basis. The 2% rate in the example applies to the assumed subsequent capitalised construction expenditure on an existing building completed between 1925 and 2022. If a separate new building is created for tax purposes, different treatment may be required. Your personal tax outcome and the timing of the saving may also differ from the model. Discuss depreciation, deductible expenditure and cash-flow planning with your tax adviser.
FAQFrequently asked questions
What is the housing fast-track?
It is a temporary provision in section 246e of the Federal Building Code (Baugesetzbuch, BauGB). Until the end of 2030, it enables departures for residential projects, for example from a local development plan, subject to municipal consent and statutory conditions. The departure must be compatible with public interests, with due consideration given to neighbours' interests. Other requirements and grounds for exclusion must still be observed.
When did the housing fast-track take effect?
The housing fast-track under section 246e BauGB took effect on 30 October 2025. It forms part of the Act to Accelerate Residential Construction and Safeguard Housing.
How long does the municipality have to give consent?
The standard period is three months from receipt of the approval authority's request. If consent is not refused within the applicable period, it is deemed granted subject to section 36a BauGB. Public consultation may extend the period by the length of the consultation, up to one month. This is not a deadline for the entire building permit process.
Does the housing fast-track cover additional storeys and loft conversions?
Yes, provided housing is created and the other statutory conditions are met. Section 246e covers extensions, alterations or renewals that create homes, as well as conversions to residential use. Approval is not automatically guaranteed.
Do state building regulations still apply?
Yes. Section 246e enables departures from the Federal Building Code and regulations based on it, but does not create a general exemption from state building regulations. The applicable rules on boundary distances, fire safety, parking and other requirements still apply.
Could my neighbour build higher under the housing fast-track?
Potentially, if the necessary consent is in place and the other statutory conditions are met. Neighbours' interests must be considered. Legal remedies against a permit depend in particular on a possible infringement of the neighbour's own legally protected rights. Seek advice from a qualified lawyer on the individual case.
When does the housing fast-track expire?
The special provision is limited to 31 December 2030. This concerns its application, rather than directly limiting the validity of a permit already granted. The permit's own validity and expiry rules still apply; submitting an application alone does not automatically secure use of the provision.
09Further reading
- Reading a local development plan
- Housing construction in 2026: completions and demand
- New-build or existing property
- Glossary: local development plan
- Data: construction price index
- Calculator: property cash flow
10Sources
- Section 246e BauGB (temporary special provision for residential construction)
- Section 36a BauGB (municipal consent)
- Act to Accelerate Residential Construction and Safeguard Housing
- Section 7 EStG (depreciation), section 32a EStG (income tax rates)
- Section 556f BGB (exceptions to the initial rent cap), section 558 BGB (rent increases up to the local reference rent)
- Worked example: own calculation using the assumptions explained in the article
This guide provides general information and does not replace individual legal, tax or investment advice. The competent authorities decide whether a proposal is approved. The illustrative calculation is neither a market forecast nor a promise of returns. Consult a qualified lawyer or tax adviser about legal and tax questions concerning your project.

Writes about Financing and calculations, Taxes and Care properties.
Michael combines his experience as a banker and former portfolio manager at a family office with his practice as a property investor himself. He writes about robust calculations, financing, risks and strategic portfolio building.
This guide does not replace tax or legal advice. All figures are example calculations with disclosed assumptions.