Financing a German New-Build Apartment: What Construction Really Costs
Coordinate staged payments, fixed-rate borrowing and cash reserves—with a fully disclosed six-month delay calculation.
01Separate construction progress, payment and drawdown
Buying a German new-build apartment from a developer requires funding before rental income arrives. The instalment arrangement under section 3 MaBV, Germany’s estate-agent and developer ordinance, provides for no more than seven payments. For the land-purchase arrangement considered here, the initial share is 30% after earthworks begin. Subsequent statutory percentages apply to the remaining 70%: the structural-shell allocation of 40% therefore equals 28% of the total price. Construction stages are grouped into payments.
Earthworks alone do not make payment due. Section 3 also requires safeguards including an effective contract, the required priority notice in the land register, secured release from relevant encumbrances and building-law prerequisites. Signing before a notary is therefore not an automatic interest start date. MaBV is not a completion guarantee.
Compare the notarised payment schedule, construction timetable and lender’s drawdown requirements. Ask which invoices, progress certificates and other documents each release requires.
02Worked example: interest before rental income
Every price, rate and date below is illustrative, not an investment offer or market forecast. Assume a €320,000 purchase, a €300,000 loan and €20,000 equity used for the first payment. Acquisition expenses are funded separately. Assumptions are 3.8% annual borrowing interest, twelve commitment-interest-free months from model commencement, then 0.25% monthly on undrawn funds. Principal repayment starts in month 20 by agreement.
| Month | Grouped construction stage | Purchase payment | Loan drawn afterwards |
|---|---|---|---|
| 1 | Earthworks | €96,000 | €76,000 |
| 5 | Structural shell, carpentry, roof and gutters | €107,520 | €183,520 |
| 8 | Heating, plumbing, electrical rough-in and windows | €42,560 | €226,080 |
| 11 | Internal plaster, screed and bathroom tiling | €29,120 | €255,200 |
| 15 | Ready for occupation, against handover | €26,880 | €282,080 |
| 17 | Façade | €6,720 | €288,800 |
| 19 | Full completion | €11,200 | €300,000 |
Payments total €320,000. Only the first includes equity. Assume all payment conditions are satisfied and drawdowns occur at each indicated month’s beginning. Rent starts in month 16 despite later outstanding works.
Disclosed calculation
This simplified model divides annual interest by twelve, with no principal repayments or compounding during construction:
- Construction-period borrowing interest, months 1–15: (76,000 × 4 + 183,520 × 3 + 226,080 × 3 + 255,200 × 4 + 282,080 × 1) × 0.038 ÷ 12 = €8,979.65.
- Commitment interest, months 13–15: (44,800 × 2 + 17,920 × 1) × 0.0025 = €268.80.
- Total before first rent: €9,248.45.
Results are rounded to cents at the end. Daily bank calculations may differ. Interest continues after month 15: this is not the total financing cost through full completion in month 19.

03Separate cash flow from tax
From principal repayment commencement, assume 65 m², monthly rent excluding service charges of €13/m², and €50 monthly for owner expenses or reserves. That €50 is a calculation placeholder, not an adequate property budget.
| Monthly assumption from month 20 | Amount |
|---|---|
| Rent: 65 × €13 | €845 |
| Owner budget | −€50 |
| Mortgage payment: 300,000 × (3.8% + 2%) ÷ 12 | −€1,450 |
| Pre-tax cash flow | −€655 |
The first payment contains €950 interest and €500 principal. Principal reduces debt but still consumes cash. Months 16–19 require a separate transitional calculation. Add actual management, maintenance, vacancy and potential special-assessment budgets using the cash-flow calculator.
Your own borrowing and commitment interest may qualify as Werbungskosten, deductible income-related expenses, even before rent starts. Section 9 EStG, Germany’s Income Tax Act, requires the relevant economic connection; objectively evidenced rental intention matters. A declaration alone is insufficient.
Do not budget for a guaranteed refund. Its amount and timing depend on individual circumstances. Assess depreciation separately: special and declining-balance depreciation. This article addresses German taxation only.
04Coordinate the fixed-rate period and funding
Confirm the exact start and end of the fixed-rate period and principal repayment commencement. If a ten-year period starts in model month 1 and repayments begin at month 20’s end, only 101 monthly payments fall through month 120. Compare ten-, twelve- and fifteen-year offers using actual pricing and projected remaining debt.
For fixed-rate borrowing, section 489 BGB, Germany’s Civil Code, generally permits termination ten years after full receipt of the loan, with six months’ notice. A subsequent agreement changing interest or repayment timing can replace that starting point. Contract signature and final drawdown are different dates.

05Financing checklist
- Timing buffer: Model six additional construction months and vacancy.
- Undrawn funds: Negotiate the interest-free period, extensions and drawdown deadline.
- Repayments: Confirm commencement and payments before full drawdown.
- Instalments: Request all charges and documentary requirements in writing.
- Equity: Compare borrowing-interest savings against commitment charges; retain cash reserves.
- Total budget: Allow separately for acquisition expenses, initial fittings and owner costs.
06Risks to examine before signing
Delay: Have deadlines and remedies reviewed in the developer contract. Compensation requires the legal conditions to be met; recovery is not automatic. Section 280 BGB additionally refers delay claims to section 286.
Insolvency and first letting: Reserve cash for construction stoppages and rental gaps. Read about developer insolvency and first letting.
Interest rates: Check each financing component’s fixed-rate coverage and stress-test refinancing at a higher rate.
Defects: Document Abnahme, formal acceptance of the works, and reserve rights concerning known defects. An appropriate withholding is distinct from whether the final instalment is due; see sections 640 and 641 BGB and the acceptance checklist.
07Bottom line
The model needs €9,248.45 before first rent, or €14,769.25 with delay. Base the decision on realistic payments, reserves and affordable cash flow after principal repayments begin—not an anticipated tax benefit.
FAQFrequently asked questions
When do interest and principal repayments start?
In the baseline example, borrowing interest starts with the first drawdown and principal repayment starts in month 20. The delay scenario additionally assumes the lender agrees to defer principal repayment until month 26; construction delay alone does not do this. Check drawdown, interest calculation and repayment dates in the loan contract.
How many developer instalments are provided for?
The instalment model under section 3 MaBV, Germany’s estate-agent and developer ordinance, provides for no more than seven payments. The first payment requires legal safeguards as well as the relevant construction progress.
Can construction and commitment interest be deducted for tax?
Your own financing costs may qualify as Werbungskosten, German income-related deductions, where a sufficiently evidenced connection to a definite rental intention exists, including before rental income starts. This does not guarantee a particular refund.
How can I limit commitment interest?
Negotiate an appropriate charge-free period and extension options. Assess equity use and loan drawdowns together: later borrowing saves drawn-loan interest in the model but leaves more undrawn funds potentially subject to commitment charges, called Bereitstellungszinsen in German.
Which fixed-rate periods should I compare?
Compare, for example, ten-, twelve- and fifteen-year offers using their actual pricing, repayment start dates and remaining debt. Focus on how much of the repayment period has fixed interest and whether your budget can withstand refinancing.
What does a six-month construction delay cost in the example?
If the final three payments move back six months and the lender also agrees to defer principal repayment until month 26, the model adds €4,848.80 in borrowing interest and €672.00 in commitment interest before first rent. The total rises from €9,248.45 to €14,769.25. Lost rent, any contract-amendment charges and other costs are excluded. Without an agreed repayment deferral, the calculation must be revised.
08Sources
- MaBV, particularly section 3
- EStG, particularly section 9; Federal Fiscal Court, IX R 19/15
- BGB: sections 280, 286, 489, 640 and 641
- KfW: Climate-friendly new construction
Dated 29 October 2026. General information on German rules, not individual financing, legal or tax advice.

Writes about Taxes, AfA (depreciation), Existing properties and Portfolio building.
Since 2020, Eduard has bought seven properties of his own and supported more than 150 clients. He writes about tax levers, property documents and portfolio building – with honest numbers instead of rosy projections.
This guide does not replace tax or legal advice. All figures are example calculations with disclosed assumptions.